The FAT/SAT Acceptance Glossary 57 REAL-WORLD TERMS · ENGLISH–CHINESE (TAIWAN USAGE)

Not textbook translations — the vocabulary actually used in acceptance protocols and on test floors, with the Traditional Chinese equivalents your Taiwanese counterparts really say. Compiled by a technical interpreter from FAT/SAT, commissioning and audit assignments. Scan it before the kickoff call; share it with your team before they fly.

01

Documents & planning

The paperwork that appears in contract annexes and emails before anyone touches the machine.

URS — User Requirement Specification
使用者需求規格書

The buyer's source document defining what the equipment must do; the final yardstick at acceptance.

FDS — Functional Design Specification
功能設計規格書

The supplier's design answer to the URS; FAT items usually trace to it line by line.

ATP — Acceptance Test Procedure
驗收測試程序書

Also "test protocol" — the document executed and signed item by item on test day.

ITP — Inspection & Test Plan
檢驗與測試計畫

Who inspects what, when; witness and hold points are flagged here.

P&ID — Piping & Instrumentation Diagram
管線與儀表圖

Said "P and I D"; one copy per person during pipe walks and valve checks.

BOM — Bill of Materials
物料清單

Rhymes with "bomb"; the unpacking inspection is checked against it.

SOP — Standard Operating Procedure
標準作業程序書

Core term shared by training and audits; usually "follow the SOP".

Redlines / redline drawings
紅線修訂圖

Field changes marked in red pen; merged later into as-builts.

As-built drawings
竣工圖

Final drawings reflecting what was actually installed; mandatory at handover.

Turnover package (TOP)
移交文件包

As-builts, test records, certificates and manuals as one handover bundle — the SAT finale.

02

Testing & verification

The highest-frequency action words while a FAT/SAT runs.

Dry run
空跑測試

No material, no fluids — sequence check first.

Wet run
帶料試車

Running with real material or liquids; the step after the dry run.

Loop check
迴路檢查

Verifying each signal loop from sensor to control system; daily bread of early commissioning.

I/O check
輸入輸出點檢

Point-by-point confirmation that PLC inputs/outputs map correctly.

Interlock
連鎖(互鎖)

"Door open = no motion" protective logic; testers say "trip the interlock".

E-stop — emergency stop
緊急停止(急停)

Always on the acceptance checklist; "hit the E-stop".

Performance test / run
性能測試

Verifying throughput, yield and precision against contractual guaranteed values.

Reliability / availability run
可靠度連續運轉測試

Tens of hours of continuous running to prove uptime; "marathon run" in semi and automotive.

Cycle time
週期時間

Time per part — one of the core acceptance numbers.

Takt time
節拍時間

The target production rhythm to meet demand; German loanword, used as-is in US plants.

FAI — First Article Inspection
首件檢驗

Full-dimension inspection of the first production piece; strictest usage in aerospace (AS9102).

Golden sample
標準樣品(黃金樣品)

The mutually approved reference piece later output is compared against.

Burn-in
燒機(老化)測試

Extended powered operation to expose early failures; common for electronics.

03

Quality & findings

The second half of every acceptance revolves around these.

Acceptance criteria
允收標準

The pass/fail line — one column next to every test item.

Deviation
偏差

Measured value off spec; recorded and dispositioned via a deviation report.

Waiver / concession
特採(讓步允收)

The buyer's written "we accept this deviation"; Taiwanese QA says 特採.

NCR — Non-Conformance Report
不符合報告

Formal filing of a non-conformity; shared vocabulary of audits and acceptance.

CAPA — Corrective & Preventive Action
矯正及預防措施

Fix-it-now plus keep-it-fixed response to findings; some say "kappa".

Punch list
缺失清單

End-of-acceptance to-fix list; one item = punch item; UK English: snag list.

Open item list
未結項目清單

Tracker of items not yet closed out; reviewed every morning meeting.

Witness point
見證點

Inspection step the buyer may attend; work continues if they don't.

Hold point
停留點(停檢點)

Mandatory stop — no proceeding without the buyer's sign-off. Harder than a witness point.

Calibration certificate
校正證書

Traceability proof for measuring instruments; often the first stack checked at a FAT.

Traceability
追溯性

Mill certs, lot numbers, serials — the ability to trace everything back.

04

Commissioning & qualification

Required vocabulary for pharma, medical-device and semiconductor equipment (GAMP world).

Commissioning
試車調試

Everything between installation and formal handover; spoken as "C&Q" with qualification.

Qualification
確效

Documented proof the equipment is installed, operates and performs correctly; Taiwan GMP circles say 確效.

IQ — Installation Qualification
安裝確效

Installed per design: utilities, piping, instruments, documents in place.

OQ — Operational Qualification
操作確效

Each function behaves per spec across its operating range.

PQ — Performance Qualification
性能確效

Consistent performance under real production conditions; the last of the trilogy.

05

Safety

The vocabulary US teams are most exacting about — mishearing costs the most here.

LOTO — Lockout / Tagout
上鎖掛牌

Isolating and locking energy sources before maintenance; OSHA core requirement, constantly on US engineers' lips.

PPE — Personal Protective Equipment
個人防護具

Safety shoes, glasses, hard hats; page one of every site induction.

Permit to work
工作許可證

Written approval for high-risk work; hot work permit for anything with sparks or flame.

Toolbox talk
工具箱會議(工前會)

The 5–10 minute safety briefing before work starts.

Safety interlock
安全連鎖

Forced-stop logic of guard doors and light curtains; always tested at acceptance.

SDS — Safety Data Sheet
安全資料表

Chemical hazard and response information; formerly MSDS.

06

Commercial & handover

Before anyone signs, these words decide how money and liability flow.

Mechanical completion
機械完工

Hardware installed, ready for commissioning; abbreviated MC.

Substantial completion
實質完工

Main functions usable, only trim work left; often tied to a payment milestone.

Provisional acceptance
暫時驗收(初驗)

Conditional acceptance after SAT; PAC = provisional acceptance certificate.

Final acceptance
最終驗收(終驗)

Formal acceptance after warranty or performance period; the FAC closes the project.

Sign-off
簽核(簽認)

Noun and verb: "sign off on the test" = countersign the record as accepted.

Retention / retainage
保留款

Final payment held until final acceptance or warranty end; typically 5–10%.

Liquidated damages (LDs)
議定違約金

Pre-agreed compensation for delay or shortfall; spoken simply as "L-Ds".

Change order
變更單

Formal change to scope, price or schedule; verbal agreement doesn't count.

Warranty period
保固期

The start date is the classic dispute: shipment, SAT or FAC — whatever the contract says.

O&M manuals
操作維護手冊

Operation and maintenance; permanent member of the turnover package.

RSPL — Recommended Spare Parts List
建議備品清單

Supplier-recommended consumables and spares; pricing often negotiated with warranty terms.

Ramp-up
產能爬坡

The climb from trial to full production; the ramp-up plan is usually the first post-SAT meeting.

※ Usage varies by industry and company. This table reflects common US-supplier practice, with UK and industry-specific variants noted. Seen it used differently on your floor? Write in.